Berry Edge, Former Consett Steelworks – Roads and Sewers – Phase 3
Scope of works:
The scheme involves construction of the infrastructure on this previously remediated site, for a joint housing venture at Berry Edge between Barratt Homes and David Wilson Homes.
The principal activities included foul and storm water drainage from connections to the Northumbrian Water sewers to first plot manhole outside the roads, all in all some 650 l/m including concrete and UPVC drainage.
Installation of road crossing ducts as detailed by the statutory service providers.
Excavation and construction of the estate roads including construction of kerb raft, brick on edge and trimming roads ready for tarmac.
Phase 2 reclamation was completed and the site transferred to Barratts Developments at the end of November 2014