Scope of works:
The scheme involved the construction of housing sub-structure and associated external works to 84 units on site. Units varied from single detached properties to 4 block, 3 storey town houses Absolute Civil Engineering Ltd are employed as a works contractor to Barratt North East.
Principal activities included:-
- Setting out of the works.
- Excavation and construction of foundations, including trench filling where required.
- Construction of ‘suspended concrete floors’ including sub-structure brickwork, insulations, internal services ducts and reinforced concrete floors.
- Construction of foul and storm water plot drainage.
- Driveways and flagged footpaths to properties.
- Construction of new public footpaths and kerbing to adopted estate roads.